Data center relocation case studies

Need proof that MIGRA works? See how these companies improved their overall business operations with our help executing their data center relocation projects.

MIGRA's move-window record

Across the two moves MIGRA has published in full, the physical work took 38 of 60 planned hours, finishing 37% faster than planned. Here is how each move compared with the window the client planned for.

Planned vs. actual move windows in MIGRA's published case studies
MoveDevicesTransportPlanned windowActualShare of plan
Managing the logistics4001,600 miles by chartered DC-9 cargo plane and truck48 hours30 hours63%
Upgrading infrastructure200Truck, over a holiday weekend12 hours8 hours67%
Both moves600 60 hours38 hours63%

Planned window is the time estimated for the physical move; actual is the time the physical move took, as reported in each case study. Figures come from the two full case studies on this page.